Hopkinton High School / Middle School

Master Plan / Design and Construction Services
Hopkinton, MA

 

Master Plan

Gale was engaged to evaluate Fields 4 and 5, Field 3 (with track) and Field 13 at the High School/Middle School Athletic Complex for a feasibility study for a synthetic turf field(s).

  • Existing conditions evaluation of each site
  • Compiled use data for each venue
  • Coordinated with Town staff and user groups to confirm use data and discuss each site’s issues and potential for upgrades
  • Reviewed turf and infill options
  • Developed schematic plans and cost estimates for each field
  • Presented Master Plan to Turf Field Committee and the community in a public forum

 

Phase 1 Design/Construction

Design, permitting, construction documents and oversite for Phase 1 consists of a large multi-purpose turf field with baseball and softball, athletic lights and ADA access and parking; estimated completion expected in the fall of 2018

 

The project was awarded a 2019 Distinguished Multi Field Award by the American Sports Builders Association (ASBA).